12-03-2014, 07:17 AM
I am sorry, I don't quite understand the question. If you mean that the plant can produce 120 MW of electricity and 210 MW process steam in backpressure mode, then your earlier data were wrong, and you should correct the parameters accordingly.
In addition, if you are really using tonnes as the unit for steam in the model, you should also take that into account in the CHPR (and CEH, if used) parameters.