(05-09-2019, 04:12 AM)Gary Wrote: Hi Chandra,

You can most certainly assign AFs that change over time by adjusting the AFAfor the ELCOA plants in the DemoS models.

You may want to take a look at the TIMES-Starter platform (https://iea-etsap.org/index.php/etsap-times-starter), which is based upon the USEPA US9r TIMES model. It has a more robust set of power plants & a comprehensive RES for the entire energy system, based initially on the USEPA/DOE data, than DemoS. You can also contact Carol Lenox (Lenox.Carol@epa.gov) requesting access to US9rT.

Dear Mr. Goldstein,

Thank you very much for clarifying my doubt. I'll follow your suggestions. 

With best regards,
Chandra
Reply


Messages In This Thread
Availability factor values - by chandra - 05-09-2019, 02:59 AM
RE: Availability factor values - by Gary - 05-09-2019, 04:07 AM
RE: Availability factor values - by Gary - 05-09-2019, 04:12 AM
RE: Availability factor values - by chandra - 05-09-2019, 10:35 PM

Forum Jump:


Users browsing this thread: 1 Guest(s)