Adding Project capacity in Future Years
#4
If the period starts in 2015 and ends in 2019, how do you suggest TIMES should make the process start in year 2018 only?

As I am sure you know, TIMES assumes that the activity levels are constant within each period, and so you are going to have a constant activity for the process from 2015 to 2019. If you want that the process activity starts accurately in 2018, you would need to redefine your periods.

 

However, if you would be satisfied in 40% of the capacity being available in this period, you can just use NCAP_ILED=3 for the process in this period.

Reply