Hi,
I am modeling thermal storage (DAYNITE) with self-discharge of 20% (S_LOSS=0.2) and an efficiency of 70% (S_EFF=0.7) when I get the results, only the efficiency seems to be taken into consideration (Ex. in year 2035 FOut(0.0126)/FIn(0.0180)=0.7).
PART II of the manual says "Timeslice storage process (EQ_STGTSS): applied to the average storage level (VAR_ACT) between two consecutive timeslices" but it does not seem to be affecting my results in this way.
In the Demos and Advance Demos there is not an example with it.
I would like to know how the S_LOSS is calculated and how can I enter 20% of self-discharge using S_LOSS attribute.
Thanks.
I am modeling thermal storage (DAYNITE) with self-discharge of 20% (S_LOSS=0.2) and an efficiency of 70% (S_EFF=0.7) when I get the results, only the efficiency seems to be taken into consideration (Ex. in year 2035 FOut(0.0126)/FIn(0.0180)=0.7).
PART II of the manual says "Timeslice storage process (EQ_STGTSS): applied to the average storage level (VAR_ACT) between two consecutive timeslices" but it does not seem to be affecting my results in this way.
In the Demos and Advance Demos there is not an example with it.
I would like to know how the S_LOSS is calculated and how can I enter 20% of self-discharge using S_LOSS attribute.